Supplement Buhriz Bridge on Diyala River in Diyala

Client: Diyala Province

POC: Director of Roads & Bridges in Diyala Province & Abniya AL-Maamora Company

Description: The project contains completion of the remaining works of the bridge. The bridge was started on 2005, but the works stopped due to security conditions on 2006. This phase contains completion all remaining works. Work includes supply and installation of 33 concrete girders spanning 24 meters each and the middle span of 48 meters steel girder.

 

Staff Details: A site office with highly experienced engineers and technicians managed the site activities. Our offices Outside Iraq supported the project by purchasing equipment and instruments, The Baghdad HQ supported vital administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. A total of 4 engineers, 35 technicians and 3 administrative personnel are covered project activities.

 

Starting Date: December 2010

Completion date: December 2011