Al Qariyah al Asriyah Bridge in Babylon
Client: Ministry of Municipality and Public Works
POC: Amer Ghazi Hilal
Description: The project Consists of designing and constructing overpass connecting Hilla-Baghdad road with Kerbala, with small bridge over iskandariyah canal and all required approaches and temporary roads. The Bridge contains 7 spans of 24 m each with very small radius due to obstacles on the area. The width of the bridge is 8m.
Staff Details: A site office with highly experienced engineers and technicians managed the site activities. Our offices Outside Iraq supported the project by purchasing equipment and instruments, The Baghdad HQ supported vital administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. A total of 4 engineers, 25 technicians and 3 administrative personnel are covered project activities.
Starting Date: June 2011
Completion Date: March 2014