You are here:

132 KVA Overhead Lines in Ramadi.

Client: Gulf Region Division-Central District

W6EX GRD Central District APO AE 09335

POC: Jose.Morales@tac01.usace.army.mil

Description: Construction of a 132 KVA overhead line from Ar Ramadi east to Hit. Four types of high tension towers were used.

Staff Details: A site office with highly experienced engineers and technicians managing the site activity was established. Outside Iraq, offices supported the project by purchasing equipment. The Baghdad and Amman offices both supported vital administration and correspondence needs. The site staff was entirely comprised of locals to encourage employment in conflict affected area. Beside dozens of skilled and unskilled workers, a total of 9 engineers, 25 technicians and 10 administrative support personnel were all part of the successful completion of this project.

Starting Date: October 2006

Completion date: March 2008