Project
name: Design and Construct Iraqi
National Guard--Suwarah Battalion facilities.
Client: CAPE Environmental
POC: James Stewart tel: +1732
610 9692, E-mail: jstewart@cape-inc.com
Description:
Design, renovation and new construction of
a 17,000m2 complex. The project includes infrastructure,
roads and training yards, and power supply
facilities. The project completed within record
time of less than 90 days.
Staff
details: A site office with highly
experienced engineers and technicians managed
site activities. Outside Iraq, offices supported
the project by purchasing equipment and Baghdad
HQ supported the administration and correspondence
needs. The site staff was mainly from the
local area to encourage employment in conflict
affected area. A total of 30 engineers, 64
technicians and 15 administrative personnel
covered the project activities. More than
1,300 of skilled and unskilled workers were
engaged from the local area.
Start
Date: Jun 2005
Completion date: September
2005

|