Project
name: Abo Teban water treatment plant
Client: Al-Anbar governorate
POC: AL-Anbar Water Directorate
Description:
supplying and installation complete water
treatment plant with capacity of 200 m3/h
includes clarifier and settling tank, filtration
vessel; feed water pumps, chlorination dosing
system, aluminum sulfate predation tank with
dosing pump, backup generators, and transformers.
They manufactured by (ARI ARITMA) Turkish
company.
Staff
details: Site office with high experienced
engineers and technicians managing the site
activities, Outside Iraq branches offices
were supporting the project by purchasing
equipment and instruments. Baghdad and Amman
offices were supporting the administration
and correspondence. All the site's staffs
that consist of tens of skilled and unskilled
workers were choosing from the local area
to encourage employment after the war that
affected the area. The main staff consists
of 3 engineers, 12 technicians and 4 administration
high educated staff covering the project activities.
Start
Date: November 2007
Completion date: may 2008

|